العنوان: Mitigating Co-Activity Conflicts and Resource Overallocation in Construction Projects: A Modular Heuristic Scheduling Approach with Primavera P6 EPPM Integration.
المؤلفون: Ninpan, Khwansiri, Huang, Shuzhang, Vitillo, Francesco, Assaad, Mohamad Ali, Benmiloud Bechet, Lies, Plana, Robert
المصدر: Algorithms; Jun2024, Vol. 17 Issue 6, p230, 11p
مصطلحات موضوعية: MODULAR construction, CONSTRUCTION projects, CONSTRUCTION project management, DIGITAL twins, HEURISTIC
مستخلص: This paper proposes a heuristic approach for managing complex construction projects. The tool incorporates Primavera P6 EPPM and Synchro 4D, enabling proactive clash detection and resolution of spatial conflicts during concurrent tasks. Additionally, it performs resource verification for sufficient allocation before task initiation. This integrated approach facilitates the generation of conflict-free and feasible construction schedules. By adhering to project constraints and seamlessly integrating with existing industry tools, the proposed solution offers a comprehensive and robust approach to construction project management. This constitutes, to our knowledge, the first dynamic digital twin for the delivery of a complex project. [ABSTRACT FROM AUTHOR]
Copyright of Algorithms is the property of MDPI and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use. This abstract may be abridged. No warranty is given about the accuracy of the copy. Users should refer to the original published version of the material for the full abstract. (Copyright applies to all Abstracts.)